9.2, 5.8, 9.8. Could we extend under DC power connector? measure max DC power\r
plus diameter (molded part) as 9.8, 8.5, 9.4mm\r
Status: Need to talk about this. RGB 09/27/14\r
+\r
+68. Pls add 480 ohm series resistors in series with BOOT0, select, and back nets.\r
\r
======================================================================================================================================================================================\r
The following should be added as items to list above & numbered. Too many places to look for possible changes. Also, there should be some means of showing resolution. RGB 09/27/14\r
2/ L1, R10, C10, C12, C11, C13 close to U1 with direct connection to p20\r
====> Parts staged to do this when PCB routing done. RGB 09/27/14\r
\r
-<<<<<<< .mine\r
3/ Large labls for connectors and trimmers. Maybe single letters or\r
symbols so they can fit? So user doesn't have to refer to schematic\r
====> Locations should be shown in "User Guide". There is a limit to component density and the number of labelling exceptions. If you want some specific labelling let me know. RGB 09/27/14\r
symbols so they can fit? So user doesn't have to refer to schematic when setting up.\r
====> Ditto\r
\r
-4/ "As per June 2001 pcd mixed signal ... " PDF\r
-====> Same as 1/ above.\r
+BOM checklist\r
+-------------\r
+\r
+[X] CN12 female box header and wire?\r
+ + should we provide some male headers? NO\r
+ + should we approach signal-link? Don't have to. Several vendors use this scheme.\r
+ [X] CN3 specified as RASM722PX Yes\r
+ [O] knob for pot: Will add to BOM\r
+\r
+Risk List\r
+---------\r
\r
- BOM checklist\r
- -------------\r
+1. [ ] Risk: Inductive kick from L3 damaging components on board. \r
+ Action: Confirm value with Matt, decide on if we should \r
+ downgrade to a bead\r
\r
- [X] CN12 female box header and wire?\r
- + should we provide some male headers? NO\r
- + should we approach signal-link? Don't have to. Several vendors use this scheme.\r
- [X] CN3 specified as RASM722PX Yes\r
- [O] knob for pot: Will add to BOM\r
+2. [ ] Risk: Untested changes in schematic leading to a major problem. \r
+ Action: David to review all change log entries above to\r
+ determine if any have been untested\r
\r
+3. [ ] Risk; Software not ready when Beta hardware arrives: Action:\r
+ Specify min software load (e.g. configuration menus, SNR read\r
+ out, set up procedure)\r